Smart Meters and Solar Panels: Do You Need a New Meter?

You don’t need a smart meter to install solar panels, but you do need one that records export to be paid for the electricity you send to the grid. Here is how the meters fit together.

By

Solar Panels London

·

Last reviewed

You don’t need a smart meter to have solar panels installed, and in most homes the existing meter doesn’t need to be physically changed by the installer. But to be paid for the electricity you export under the Smart Export Guarantee, you need a meter that records export in half-hourly readings, which normally means a smart meter. If you don’t have one, your energy supplier can install one.

Key points

  • Solar panels can be installed with or without a smart meter.

  • Smart Export Guarantee payments need a meter capable of half-hourly export readings, normally a smart meter.

  • Your SEG tariff doesn’t have to come from the company that supplies your electricity.

  • Your installer notifies the network operator about the system. That is separate from your meter.

  • On Feed-in Tariff systems, a generation meter measures what the panels produce, and some upgrades change the metering.

Why the meter matters

When your panels produce more than your home is using, the surplus flows out to the grid. Your supply meter sits at the point where your home connects to the network, so it is the meter that can measure that export as well as what you import.

A smart meter records import and export separately, in half-hour periods, and sends the readings to your supplier automatically. That is what Smart Export Guarantee suppliers need to pay you.

Illustration of electricity flowing in two directions through a meter: import from the grid and export to the grid

What you need for Smart Export Guarantee payments

According to GOV.UK, to receive a Smart Export Guarantee (SEG) tariff you need:

  • An installation certified under the Microgeneration Certification Scheme (MCS) or an equivalent scheme.

  • A meter capable of providing half-hourly export readings, which would typically be a smart meter.

Ofgem’s guidance also says the export meter must be at the point where your installation connects to the grid, and that SEG suppliers can only start paying once they can get your export readings.

You can choose any SEG supplier, not just your electricity supplier, and you can only have one SEG tariff at a time. Our guide to the Smart Export Guarantee explains how to choose one, and our guide to what an MCS certificate is explains the certificate.

If you already have a smart meter

Usually nothing needs to change on the meter itself. Once the system is installed, you apply for an SEG tariff, and the supplier sets up export readings from your meter. It can take a little time before export readings start coming through, and you may be asked for a manual reading at the start.

If you don’t have a smart meter

Ask your energy supplier to install one. You can still have the solar panels installed first, but you won’t be paid for exports until a suitable meter is in place and set up for export.

Generation meters

A generation meter measures the total electricity your panels produce, before any of it is used or exported. On Feed-in Tariff systems, it is the meter your FIT payments are based on, so it matters a great deal. On newer systems, generation is usually also visible in the inverter’s monitoring app.

Illustration of a meter cupboard with a supply meter, a generation meter and an inverter

Request a solar and battery quotation

Send your details and we’ll call you back to arrange a free survey.

We install across London and up to around 50 miles out.

No obligation. We’ll call you back within one working day (Mon–Fri, 9am–5pm). We only use your details to deal with your enquiry. See our privacy policy.

Feed-in Tariff systems

If your system is on the Feed-in Tariff, you are paid for generation, using your generation meter readings, and usually for a deemed amount of export too. Some upgrades change how generation is measured:

  • Adding an AC-coupled battery alongside your existing inverter normally leaves the FIT generation meter unaffected.

  • Replacing the inverter with a hybrid that also runs a battery changes how generation passes through the system. Our standard practice in that case is to fit a bidirectional meter, subject to checking your system.

Your FIT licensee should be told about changes before and after the work. Our guides to keeping your Feed-in Tariff when you upgrade and the Feed-in Tariff for solar owners explain the rules.

The network operator is a separate step

Your installer notifies or applies to the local network operator (DNO) for the solar system, and for any battery. This is about the connection to the grid, not about your meter. Our guide to DNO rules and export limits explains G98 and G99.

Frequently asked questions

Will my old meter run backwards with solar panels?

Some older meters can record exported electricity incorrectly. If you still have an older non-smart meter, tell your energy supplier when solar is installed, so they can check it and arrange a smart meter if needed.

Do I need to tell my energy supplier I have solar panels?

Yes, it’s sensible to tell them, especially if you want an export tariff or have an older meter. Your installer deals with the network operator, but your supplier handles your meter and tariff.

Does a battery need its own meter?

Usually not. A battery sits on your side of the supply meter, and its charging and discharging show up in the inverter’s monitoring. On some upgrades to Feed-in Tariff systems, the metering arrangement changes, as explained above.

Can I see my export on the in-home display?

Many smart meter displays only show import by default. Your export readings are still recorded and sent to your supplier. Your inverter’s monitoring app usually gives a clearer picture of generation, use and export. Our guide to getting your solar monitoring app back online helps if it has stopped working.

Getting it set up properly

We handle the MCS certificate and the network operator paperwork, and explain what to ask your supplier for at handover. Request a solar and battery quotation to get started.

Request a solar and battery quotation

Send your details and we’ll call you back to arrange a free survey.

We install across London and up to around 50 miles out.

No obligation. We’ll call you back within one working day (Mon–Fri, 9am–5pm). We only use your details to deal with your enquiry. See our privacy policy.

Latest Articles

Ready to Start Saving with Solar?

Get your free no-obligation quote today. Our experts will design the perfect system for your home.

Free Home Survey

MCS Certified

Reply in 1 Working Day

© 2026 Solar Panels London. All rights reserved.

SOLAR PANELS LONDON (SPL) LIMITED, registered in England and Wales, company number 14360308. Registered Office, 20 Rosslyn Crescent, Luton, LU3 2AU. SOLAR PANELS LONDON (SPL) LIMITED is an Introducer Appointed Representative of Shermin Finance Limited, FRN 727594, company number 01276121. Registered Office, Homeserve, Cable Drive, Walsall, WS2 7BN. Shermin Finance Limited act as a credit broker and is not a lender. Credit is subject to status and affordability.