The Commercial Solar Installation Process, Step by Step
A commercial solar project runs from assessment and design through grid approval, installation, commissioning and handover. What happens at each stage and what usually sets the timetable.
By
Solar Panels London
·
Last reviewed
A commercial solar project normally runs through eight stages: enquiry, site assessment, design and proposal, approvals, contract and planning of the works, installation, commissioning, and handover with ongoing maintenance. The installation itself is often the shortest part. The timetable is usually set by how quickly electricity data and building information are available, whether a structural report is needed, and, for larger systems, the network operator’s response to the grid application.
This guide explains each stage and what your business needs to do. For homeowners, our guide to the solar installation process step by step covers domestic projects.
Key points
Half-hourly electricity data is the most useful thing you can provide at the start.
Structural checks and the grid application are the stages most likely to affect timing.
Commercial clients have duties under the Construction (Design and Management) Regulations 2015.
Most roof work can go ahead while the building is in use, with a short planned power off for the final connection.
You should receive a full handover pack, including test certificates and monitoring access.
1. Enquiry
You tell us about the site: the address, who owns the roof, the type of building and what you want to achieve. It helps to send half-hourly electricity data for the last 12 months, which your supplier or meter operator can usually provide. If you don’t have it, recent bills are enough to start. You can send this through our commercial solar assessment page.
2. Site assessment
We look at the building and how it uses electricity:
The roof: area, orientation, pitch, shading, covering, condition and remaining life, and any fragile areas such as rooflights.
The structure: whether it can carry the extra load. On some buildings this needs a structural engineer’s report, which we arrange.
The electrics: the intake, switchgear and distribution boards, and where inverters, isolators and any battery can go.
Access: how equipment and people will reach the roof safely.
Planning: permitted development limits, conservation areas and listed status.
For older buildings, the asbestos register should be checked before any roof work. Our guide to solar on warehouse and industrial roofs explains the roof and structural checks in more detail.
3. Design and proposal

We design a panel layout that keeps clear of rooflights, roof plant and access routes, and size the system against your daytime use and the likely export limit. The proposal sets out:
The system design, with panel layout, inverter and any battery options.
Expected annual generation, and how much of it your site is likely to use.
Purchase and power purchase agreement (PPA) options side by side. We offer PPAs through a funding partner.
The grid connection route and a realistic timetable.
Anything to resolve first, such as roof repairs or a structural check.
We don’t put savings figures in front of you until they are based on your own data. Our guide to what affects the cost of commercial solar explains what drives the price.
4. Approvals
Grid connection. Most commercial systems need a G99 application to the network operator before they can be connected. We prepare and submit it. The network operator may approve the full export, set an export limit or require network works, and it sets the timetable for its response. For larger systems this is often the longest stage. Our guide to commercial solar and G99 explains the process.
Planning. Many rooftop systems on commercial buildings are permitted development. Where they aren’t, for example on some listed buildings or larger ground-mounted arrays, a planning application is needed.
Landlord consent. If you lease the building, the landlord’s written consent is usually required. See our guide to solar on leased and multi-let buildings.
Insurer. Tell your insurer about the planned installation. Many will ask how fire safety has been considered.
Request a commercial solar assessment
Tell us about your premises and we’ll call you back to talk through solar and battery storage for your site.
We install across London and up to around 50 miles out.
5. Contract and planning the works
Once the design and approvals are settled, the contract confirms the system, programme and responsibilities. Before work starts we agree:
Access routes, delivery times and any exclusion zones.
Scaffold, edge protection, netting or MEWP positions.
Where welfare facilities and materials storage will go.
The date and length of the planned power off for the final connection.
Risk assessments and method statements for the work.
Your duties as a commercial client. Under the Construction (Design and Management) Regulations 2015, a business commissioning construction work has client duties, including making suitable arrangements for managing the project and providing relevant information about the building, such as the asbestos register, known fragile areas and drawings. We explain what this means for your project at the start.
6. Installation
The usual order is access first, then mounting, panels, cabling and inverters, then the electrical connection. Roof work can usually go ahead while the building is in use, with exclusion zones below the work area. On larger sites the installation can be phased to keep parts of the building clear. The final connection into your switchgear normally needs a short planned power off, scheduled around your operations.
7. Commissioning
The system is tested before it is switched on for good. That includes electrical testing of the DC and AC sides, checks on protection and isolation, and confirming that the inverter settings meet the network operator’s requirements, including any export limit. Where required, the network operator is notified that the system has been commissioned.
8. Handover and maintenance

At handover you should receive:
Electrical installation and test certificates.
An MCS certificate for systems up to 50kW installed under MCS. Larger systems fall outside the MCS installation standard. Our guide to MCS certificates explains what this covers.
Equipment datasheets, warranties and an as-installed layout.
Monitoring access, so you can see generation and spot faults.
Operating and isolation instructions for your site team.
Commercial systems benefit from planned maintenance, including inspection, testing and cleaning where needed. Our commercial solar maintenance page explains what that involves. Under a PPA, maintenance is covered by the funder for the term.
FAQs
How long does a commercial solar project take?
It depends mostly on the grid application, any structural or roof work, and how quickly data and approvals come through. The installation is usually the shortest stage. We give you a realistic timetable in the proposal.
Will installation disrupt our business?
Usually very little. Roof work goes on above an operating building with agreed exclusion zones, and the final connection needs a short planned power off at a time that suits you.
Do we need to do anything before the survey?
Gather your electricity data or bills, any roof drawings and structural information, and the asbestos register if the building has one. Tell us about anything planned, such as a re-roof or new equipment.
Can a battery be added later?
Often yes, especially if it is planned for at the design stage. Our commercial battery storage page explains the options.
Request a commercial solar assessment
Tell us about your premises and we’ll call you back to talk through solar and battery storage for your site.
We install across London and up to around 50 miles out.
Latest Articles
Ready to Start Saving with Solar?
Get your free no-obligation quote today. Our experts will design the perfect system for your home.
Free Home Survey
MCS Certified
Reply in 1 Working Day
Quick Links
Services
Contact
© 2026 Solar Panels London. All rights reserved.
SOLAR PANELS LONDON (SPL) LIMITED, registered in England and Wales, company number 14360308. Registered Office, 20 Rosslyn Crescent, Luton, LU3 2AU. SOLAR PANELS LONDON (SPL) LIMITED is an Introducer Appointed Representative of Shermin Finance Limited, FRN 727594, company number 01276121. Registered Office, Homeserve, Cable Drive, Walsall, WS2 7BN. Shermin Finance Limited act as a credit broker and is not a lender. Credit is subject to status and affordability.