Solar Panels on Warehouse and Industrial Roofs: What to Check First
Most warehouse and industrial roofs can take solar, but the roof sheet, fragile rooflights, structural capacity and remaining roof life need checking first. Here is what to look at before you commit.
By
Solar Panels London
·
Last reviewed
Most warehouse and industrial roofs can take solar panels, and they are often some of the best roofs for it: large, unshaded and above a building that uses electricity during the day. Before a system is designed, though, five things need checking: what the roof is made of, where the fragile areas are, whether the structure can carry the extra load, how long the roof has left, and how the system will connect to the grid. Getting these right at the start avoids redesigns, delays and arguments with insurers later.
This guide explains each check. For how we approach warehouse sites specifically, see our solar for warehouses page.
Key points
Profiled metal sheet roofs are the most common and usually the simplest to fit, with clamps that suit the sheet profile.
Fibre cement roofs need extra care. They are often fragile, and older sheets may contain asbestos.
Rooflights should be treated as fragile and protected throughout the work.
A structural check confirms the roof can carry the panels, the mounting and wind loads.
Most commercial systems need a G99 application to the network operator before connection.
Tell your insurer before installation, and expect them to ask how fire risk has been managed.
What is your roof made of?
The roof covering decides the mounting system, the fixing method and how much preparation is needed.
Profiled metal sheet (trapezoidal or standing seam). The most common roof on modern warehouses and industrial units. Trapezoidal sheets take rail systems clamped or fixed to the ridges of the sheet, with sealed fixings. Standing seam roofs can often take clamps that grip the seams without drilling the sheet at all, which helps protect the roof warranty.
Fibre cement sheet. Common on older industrial buildings and farm buildings. Fibre cement is usually fragile, and sheets installed before 2000 may contain asbestos. That does not always rule solar out, but the sheet needs identifying, and an asbestos survey is needed before any work that could disturb it. In many cases replacing or over-cladding the roof first is the better long-term answer.
Flat membrane or built-up roofs. Often found on offices, trade counters and newer industrial units. These usually take ballasted mounting that sits on the roof without penetrating the waterproofing. We use Van der Valk systems on flat roofs. Our guide to solar panels on flat roofs explains the options.

Fragile roofs and rooflights
The Health and Safety Executive treats falls through fragile roofs and rooflights as one of the most serious risks in roof work. Its guidance is that a roof should be treated as fragile until a competent person has confirmed it isn’t. Materials commonly found to be fragile include:
Rooflights, especially those set into the roof plane, which can be hard to spot or painted over.
Unreinforced fibre cement sheets.
Corroded metal sheets.
Liner panels on built-up roofs.
On a warehouse this shapes the whole job. The design keeps panels and walkways clear of rooflights where possible, rooflights are covered or guarded while work is under way, and access is planned using edge protection, safety netting, staging or mobile elevating work platforms (MEWPs) as the roof requires. As the building owner or occupier, you should expect your installer to ask about known fragile areas and to agree how the site will be managed while work is going on.

Can the structure take the weight?
Solar adds a steady load across the roof, plus wind uplift that pulls on the fixings. Lightweight portal frame buildings, which many warehouses are, are often designed with a modest margin for extra roof load, so this cannot be assumed.
A structural check looks at the roof frame (purlins and rafters), the sheet and its fixings, and the extra load from panels, rails and, on flat roofs, ballast. On larger or older buildings this means a structural engineer’s report, which we arrange as part of the assessment. If the original drawings or calculations for the building are available, they speed the check up.
How long does the roof have left?
Solar panels are designed to keep working for 25 years or more. If the roof covering is likely to need replacing within that time, it is usually cheaper and less disruptive to do it first than to remove and refit the panels later. Signs that a metal roof needs attention include rusting cut edges, failed fixings, leaking laps and failing coatings. Our guide on whether you need a new roof before solar explains the trade-off, and the same logic applies to commercial roofs.
If the building is leased, the roof may belong to the landlord, which affects who decides. See our guide to solar on leased and multi-let buildings.
Request a commercial solar assessment
Tell us about your premises and we’ll call you back to talk through solar and battery storage for your site.
We install across London and up to around 50 miles out.
The grid connection
Large roofs can hold large systems, and most will need a G99 application to the network operator before they are connected. The operator may approve the full export, set an export limit, or say that network works are needed first. That decision can affect the size of system that makes sense and the timetable. Our guide to commercial solar and G99 explains the process.
Warehouses with steady daytime loads, such as lighting, chillers, forklift charging or production equipment, usually use most of their solar on site, which is where it is worth most. Where a lot of generation would be exported, a battery or an export limit may be part of the design. Our commercial battery storage page covers that.
Planning permission
Rooftop solar on many commercial and industrial buildings is permitted development, so it doesn’t need a planning application, provided it meets set limits. Listed buildings, sites in conservation areas and some other protected locations have extra restrictions. We check the planning position for your site during the assessment. If you want formal confirmation, you can apply to the local planning authority for a Lawful Development Certificate.
Fire safety and insurance
Tell your insurer before installation. Many commercial insurers refer to RC62, the joint code of practice on fire safety with solar panel installations published by the Fire Protection Association (FPA), and may ask how the system has been designed and installed in line with it. Things they commonly ask about include where the DC cables run, where isolators are placed, separation from rooflights and roof features, and how the system will be inspected and maintained. Our article on whether solar panels are a fire risk explains what the UK evidence shows about the causes of solar fires.
A planned maintenance regime helps here too. Our commercial solar maintenance page explains what that involves.
What to have ready before an assessment
The site address and who owns the roof.
Half-hourly electricity data for the last 12 months if you have it, or recent bills.
Any roof drawings, structural calculations or previous roof surveys.
An asbestos register, if the building has one.
Anything planned, such as a re-roof, extension, new machinery or EV charging.
Our commercial solar assessment page explains what we look at and what you get back. For the factors that drive the price of a system, see what affects the cost of commercial solar.
FAQs
Can solar go on an asbestos cement roof?
Sometimes, but only after the sheets have been surveyed and the risk assessed, and fitting directly onto them is often not the best option. Replacing or over-cladding the roof first is usually the safer long-term choice. Any work that could disturb asbestos must follow the asbestos regulations.
Will drilling the roof affect the warranty?
It can. Some roof systems, particularly standing seam, can take clamps that don’t penetrate the sheet. Where a roof is still under a manufacturer’s warranty, the mounting method should be checked against the warranty terms before installation.
Do we have to stop work while the system is installed?
Usually not. Roof work can go on while the building is in use, with access and exclusion zones agreed in advance. The final connection normally needs a short planned power off, which we schedule around your operations.
Is a commercial warehouse system MCS certified?
Systems up to 50kW can be installed under MCS. Larger systems fall outside the MCS installation standard and are designed and commissioned to the relevant electrical and grid connection standards instead.
Request a commercial solar assessment
Tell us about your premises and we’ll call you back to talk through solar and battery storage for your site.
We install across London and up to around 50 miles out.
Latest Articles
Ready to Start Saving with Solar?
Get your free no-obligation quote today. Our experts will design the perfect system for your home.
Free Home Survey
MCS Certified
Reply in 1 Working Day
Quick Links
Services
Contact
© 2026 Solar Panels London. All rights reserved.
SOLAR PANELS LONDON (SPL) LIMITED, registered in England and Wales, company number 14360308. Registered Office, 20 Rosslyn Crescent, Luton, LU3 2AU. SOLAR PANELS LONDON (SPL) LIMITED is an Introducer Appointed Representative of Shermin Finance Limited, FRN 727594, company number 01276121. Registered Office, Homeserve, Cable Drive, Walsall, WS2 7BN. Shermin Finance Limited act as a credit broker and is not a lender. Credit is subject to status and affordability.